摘要
对武钢6号高炉(3200m3)开炉及快速达产的经验进行了总结。武钢6号高炉采用了最新一代PW并 罐无料钟炉顶、串联软水密闭循环冷却、陶瓷杯、铜冷却壁及高温内燃式热风炉等先进技术。在开炉生产中,注 重选择合适的开炉料与配比,进行料面测量,确定合理的送风制度和装料制度,优化高炉操作,确保炉况稳定顺 行,从而使6号高炉开炉顺利,并实现快速达产。
The experiences in bolwing-in of WISCO’s No.6 blast furnace (3200m 3) and experiences in gaining target output were summarized. Some advanced technologies was applied at WISCO’s No.6 blast furnace , such as new generation of bell less top with parallel hopper which is of PW’s technology, serial closed loop soft water circulation cooling system, ceramic cup, copper cooling stave and high temperature internal combustion hot air stove. At the blowing-in period , a series of measures, such as proper selection of blowing-in burden and blending ratio, stock level measurement, rational operation regulations of hot air blowing and burden charging as well as optimized furnace operation allow smooth and stable furnace operation status, make the furnace start successfully and reach the target output rapidly.
出处
《炼铁》
北大核心
2004年第6期7-11,共5页
Ironmaking