摘要
火电厂烟气脱硫工程往往是在场地或其他条件受到诸多限制的情况下进行的,设计中总平面布置的作用显得尤其突出。以几个电厂脱硫工程的设计为例,探讨如何充分利用已有条件,协调脱硫与整个厂区总平面布置的关系,以使设计合理,经济。
The FGD project of fossil fuel power plant is usually carried out in the situations when the site and other conditions are greatly restricted.Therefore,the design,especially the general arrangement,plays an important role.In this article,the designs of several power plant FGD projects are used as examples to explore how to make full use of the existing conditions to coordinate the relation between desulfurization and the general arrangement of the whole plant area. The design will be reasonable and economical.
出处
《电力环境保护》
2004年第4期15-16,共2页
Electric Power Environmental Protection
关键词
烟气脱硫
总平面布置
因地制宜
FGD
general arrangement
taking measures suited to local conditions