摘要
介绍了秦山三期核电站辅助锅炉汽包给水控制系统,分析了其存在的不足之处,提出了优化方案。优化后的控制系统确保了辅助锅炉的平稳安全运行,同时也为其用户的正常运行提供了保障。
This paper described the feed water control system of the auxiliary boiler steam drum in Qinshan phase III nuclear power plant, analyzed the deficiency of the original configuration, and proposed the optimized configuration. The optimized feed water control system can ensure the stable and safe opera-tion of the auxiliary boiler, and the normal operation of the users.
出处
《核动力工程》
EI
CAS
CSCD
北大核心
2004年第6期525-528,共4页
Nuclear Power Engineering
关键词
辅助锅炉
控制
功能块
组态
Auxiliary boiler,Control,Function block,Configuration