摘要
本文参照国外有代表性的两座同类已建工程的原型观测成果,针对工程特点,就成屏一级电站混凝土面板堆石坝监测项目的选定,测点的布置等,作了系统地介绍.目前,部分监测设备已获初步观测成果,正为指导施工发挥作用.
This paper, consulting the observations of two similar dams abroad, gives a systematic introduction to how to choose the observation points and the items for the observation of the concret-faced rockfill dam of the Chengping Hydropower Station-I, based on the characteristics of the dam project. Now, some results have been obtained, which are playing a guiding role in the construction of the dam.
出处
《大坝观测与土工测试》
北大核心
1989年第1期26-30,共5页
Dam Observation and Geotechnical Tests