摘要
我国首条 75 0kV六分裂输电线路示范工程已在西北地区开工建设。根据该线路运行电压高、海拔高和六分裂布线结构的特点 ,在研制该线路配套金具的过程中 ,对材料、工艺及结构有所创新 ,促进了电力金具的技术进步及与国际先进水平的接轨 ,提高了金具产品的技术性能 ,降低了金具的生产成本和运输费用。
The demonstration project of the first 750 kV 6-bundle transmission line has started its construction in northwestern region of China. According to the operating characteristics of the line, such as high voltage, high elevation above sea level and 6-bundle conductor configuration, the technical renovation on material, procedure and structure has been carried out in the process of developing its completed hardware, which has promoted the technical progress of the power hardware and link to the international advanced level, increase the performance of the products and reduced their cost and transportation fee. The research achievement can be referred for future design and research of the hardware used for EHV transmission engineering.
出处
《电力建设》
2005年第1期39-42,共4页
Electric Power Construction
关键词
750
kV六分裂输电线路
金具
研制
技术创新
kV 6-bundle transmission line
hardware
development
technical renovation