摘要
对水渣码头堆取料机回转大轴承的原检修方式进行了分析 ,提出了新的检修方式 ,并对分解方案进行了细化 ,对关键部位的强度进行了验算 ,对新旧方案的优劣进行了比较。
Previous checking and repairing scheme for the slewing ring in bucket wheel stacker/reclaimer at a terminal is described and a new one is proposed.Specific dismantling procedures are presented and checking calculations of stress in key positions of the slewing ring are conducted.Comparison of new and previous schemes is performed.
出处
《起重运输机械》
北大核心
2005年第1期46-48,共3页
Hoisting and Conveying Machinery