摘要
水口1号机系卡普兰机组,结构新、工艺新、控制方式新,安装净工期16个月。监理人员从设计至投产进行“三控制”。水口1号机监理的主要经验教训是:要确保安装进度、质量,首先要进行设备监造;一定要坚持质量第一,高标准,严要求;要加强安装计划的目标管理和精神、物质激励。
The capacity of the Kaplan turbine unit at the Shuikou hydropower plant is the largest of its kind in the world. Its thrust bearing is also among the world's largest. Controlling the progress and quality of equipment manufacture and erectio is the key to the superintendence on the electromechanical engineering.
出处
《水力发电》
北大核心
1993年第12期63-65,共3页
Water Power
关键词
水电站
机电安装
工程监理
the Shuikou project, electromechanical installation, experience and lesson