通过详细的设计核算和周密的施工安排,仅和4个月时间,在不影响江阴港#2码头装卸作业的情况下,成功的将该码头接长浚深为万吨级泊位。
Through detailed design accounting and careful arrangement of construc-tion, under the condition of not affecting the handling operation of the origi-nal No.2 Wharf of Jiangyin Port, tbe wharf was lengthened and dredged toa 10000 dwt berth within a period of only 4 months.
出处
《水运工程》
北大核心
1993年第11期19-22,共4页
Port & Waterway Engineering