摘要
介绍了安徽海螺集团铜陵2条万吨生产线(A线和B线)矿区相邻的伞形山和敕山的地质概况和矿区现状,详细介绍了A,B线矿山扩建整体设计方案。从投运情况看,矿山扩建总体方案优化,挖掘和破碎设备选型配置合理。
Anhui Conch Group has two ten-thousand-ton production lines in Tongling--A and B line, the state and geology of their raw material mine of two neighbouring hills are introduced. And the holistic design scheme of A and B production line is introduced in detail. From the production condition we can see that the holistic design scheme optimization and and the configuration of digging and breaking equipments are reasonable.
出处
《水泥工程》
CAS
2005年第1期24-27,37,共5页
Cement Engineering