摘要
双联拱隧道跨度较大,造价相对较高,设计时为节省造价,洞口石方明挖量较大。以明挖代替暗挖,这在施工干扰小、环保要求小的地方是可行的,但在施工干扰较大,如建筑物密集、靠近道路等地方就不合适。因此,要根据实际情况选择明挖与暗挖,以图达到优化设计及施工的目的。
The portal section of Yinzishan double-arch tunnel was planned to construct by using cut- and-cover method. However, considering the large amount of excavation by open-cut, the disturbance of traffic on a road nearby, the existence of surface buildings and especially environmental protection, mined excavation of this section was adopted instead of open-cut.
出处
《现代隧道技术》
EI
北大核心
2005年第1期77-80,共4页
Modern Tunnelling Technology
关键词
双联拱隧道
明挖暗做
设计
施工
Double-arch tunnel
Mined excavation instead of open-cut
Design
Construction