摘要
本文重点探讨在无法排净孔底积水,也不允许采取其他有效措施的情况下利用1-2个工程桩当做降水桩孔的挖孔桩施工经验,以供同行讨论。
The paper mostly introduces some construction experiences of using one or two project pile as water-lowering well under the case that can't empting the water of the pile, and no other effectual measure can be used, for the discuss with other experts.
出处
《丹东纺专学报》
2003年第3期39-40,共2页
Journal of Dandong Textile College