摘要
对地下连续墙槽段节点采用钢板封口及外包帆布的施工新工艺,提高了构造的抗渗漏性能,也加快了施工速度。
Groove joints are sealed by sheet steel and wrapped with canvas. This new construction technology improves anti-seepage property as well as expedite construction speed.
出处
《建筑施工》
1994年第4期12-15,共4页
Building Construction
关键词
地下连续墙
槽段
节点
施工方法
underground continuous wall
groove
joint
construction