摘要
根据充填料管道输送试验提供的数据,对管道输送的有关参数进行计算,提出了合理的参数范围:流速为每秒3至3.5m;流量为每小时87至100m ̄3;重量浓度尾砂胶结充填时为71%至75%,尾砂加河砂胶结充填时为71%至73%。
Inaccordance with the data provided in the pipeline transport test of the fillingmaterial , the concerned parameters of pipeline transport are calculated and their rationalranges are proposed,i.e. flow rate variates from 3 m/s to 3.5m/s;discharge-from 87m ̄3/hr to 100 m ̄3/hr;using tailing cemented backfilling material,its weight density is 71~75 per-cent; using tailing-sand cemented backfilling material,the value is 71~73 percent;
出处
《矿业研究与开发》
CAS
北大核心
1994年第2期1-3,共3页
Mining Research and Development
关键词
胶结充填法
管道输送
铜矿床
Cemented filling, Pipeline transport, Working pressure, Hydraulic slope