摘要
变压器并列运行的条件之一是结线组别相同。因此,Y_0/△一5结线的变压器不能与Y_0/△一11结线的变压器并列运行,但是在不改变变压器内部结构及结线的情况下,采用双交心接线,即改变Y_0/△一5变压器输入、输出电压的相序,就可以与Y_0/△一11变压器并列运行。
One of the conditions of transformers shunt operation is that the groups of connecting wires are the same so that the shunt operation of a Y0/△一5 trans-former and a Y0/△一11 transformer is not allowed.But in this case the shunt ope ration lnay be allowed if double cross-junction be adopted,i.e,by clianging the output and input voltage phase order of Y0/△一5 transformer,and unnecessarily changing it's inside constructiOn and connecting wires.
出处
《山东建筑工程学院学报》
1994年第1期44-48,共5页
Journal of Shandong Institute of Architecture and Engineering
关键词
变压器
并列运行
双交心接线
transformer
shunt operation
double cross-junction