摘要
本文作为《模拟发电机组原动系统仿真》的续篇,针对其中存在的关于调速系统模拟的遗留问题.进一步分析研究了调速系统原型的主要特性,同时根据模拟实现的可行性,重新确定了模拟系统框图,并详细地介绍了其中主要模拟环节研究结果。
As the continuation of the paper 《The Simulation of the Prime Mover Systems of Dynamic Turbine-Generator Simulators》 this paper further analyzes main characteristics of the prototype of the speed-governing system. Based on the possibility of modelling, the block diagram of the modelling system is re-determined and the results of main modelling links are described in detail.
出处
《天津大学学报》
EI
CAS
CSCD
1989年第1期80-86,共7页
Journal of Tianjin University(Science and Technology)
关键词
发电机
同步发电机
调速系统
模拟
turbine-generator, simulation, speed-governing system