摘要
本文根据“金沙江溪洛渡、向家坝水电站‘西电东送,初步研究”的研究成果及溪洛渡、向家坝水电站可行性研究资料。分析了先建溪洛渡水电站或先建向家坝水电站两种开发顺序方案的优缺点及存在的问题。提出先建溪洛渡水电站的建议,提供领导及上级机构决策时参考。
Based On research achievement from preliminary study on transmitting electricity from West Chinato East China by Xiluodu and Xiangjiaba Waterpower Stations and feasibility study on Xiluod and XiangjiabaWatepower Stations,the disadvantages and advantages and the existed problems are compared in twoschemes,e·g·construct Xiluodu first or construct Xiangjiaba first. Finally, the proposltion of constrctingXiluodu first was provided for the reference to leaders and higher authorities when decisions are made.
出处
《四川水力发电》
1994年第3期29-33,83,共6页
Sichuan Hydropower
关键词
梯级水电站
防洪
水库淤积
航运
developing sequences,ctirrent price of capital cost, economy benifit
flood control, reservoirsediment,navigation.