摘要
结合某工程实践 ,通过采用桩土共同作用的复合地基托换技术 ,充分地利用原有基础的承载能力 ,很好地解决了因混凝土失效引起的基础承载力不足。最后 ,给出了典型算例供工程技术人员参考。
According to a project practice, by using the composite foundation underpinning technology, as well as considering pile-soil interaction, the problem of foundation capacity scarcity because of the failure of concrete has been solved. The original foundation has been taken into account sufficiently. In the end, a typical project example is also provided for engineers and technicians′ reference.
出处
《工业建筑》
CSCD
北大核心
2005年第3期90-92,共3页
Industrial Construction