摘要
通过对滨州黄河公路大桥南引桥百米深桩的施工 ,摸索出一套行之有效的施工方法 ,从而为该桥的顺利竣工创造了条件和奠定了基础。现简单阐述了对百米深桩倾斜、坍孔。
A set of effective methods have been developed through the construction of 100 m deep piles for the south bridge approach of Binzhou Yellow River highway bridge, which created conditions and laid down a foundation for the successful completion of the highway bridge. In this paper, the preventive construction measures for the main 100 m deep pile accidents including obliquity, cave-in and pile rupture are briefly described.
出处
《海岸工程》
2004年第4期55-59,共5页
Coastal Engineering
关键词
钻孔灌注桩
泥浆指标
倾斜度
坍孔
bored cast-in-situ pile
mud index
degree of inclination
cave-in