介绍了首钢动力厂原循环冷却水工艺的弊端,通过改变其供水方式,加水稳剂和保证供水水质等措施,节约了能源和水资源。
The shortcomings of the original circulation cooling water process of the Power Plant, Shoudu Iron & Steel Co. are presented. Variation of water supply mode, addition of water stabilizer and assurance of water quality have resulted in saving a lot of energy and water sources.
出处
《冶金动力》
2005年第2期63-65,共3页
Metallurgical Power
关键词
循环冷却水
供水工艺
冷却塔
circulation cooling water
water supply process
cooling tower