摘要
结合朝阳东大桥工程实际 ,对工程项目建设过程中各个阶段业主合同管理的主要内容及关键问题进行了较为系统的阐述 ,目的是理清思路 。
From the reality of Chaoyang Dongda Bridge project,the paper elucidates systematically the principal contents and the critical problems concerning the owner contract management at every stage in project building.The purpose lies in clearing the correct thinkings so as to have a definite object in view in owner contract management,which are used for reference to same traders.
出处
《辽宁交通科技》
2005年第3期79-80,F003,共3页
Liaoning Communication Science and Technology
关键词
业主
管理
工程项目建设
关键问题
思路
目的
过程
主合同
阶段
内容
Owner contract management Invitaion to binder and binder Measurement and payment Variation Claim