结合 110kV变电站的发展历史,综合分析了GIS和COMPASS电气设备、户内和户外布置形式以及无人值班变电站和综合自动化系统的优缺点,提出顺德地区新建 110kV变电站采用110kVGIS设备、主变户外布置的半户内布置形式和综合自动化系统。
Combining with the development history of 110kV substation, this paper analyzes the virtues and shortcomings of GIS and COMPASS electric equipment, indoor and outdoor disposition mode, unattentive substation and comprehensively automatic system. It puts forward to use 110kV GIS equipment, semi-indoor disposition(transformer outdoor) and comprehensively automatic system in Shunde new substation.
出处
《河北能源职业技术学院学报》
2005年第1期74-75,77,共3页
Journal of Hebei Energy College of Vocation and Technology