介绍了南京奥体中心主体育场工程施工测量过程中的重点和难点,重点介绍了平面控制网的建立及精度,同时还介绍了该工程特殊部位的测量定位工作。
In this article,authors introduce key points and difficulties of the construction measure process of the main stadium project of Nanjing Olympic Sports Center,emphasize establishment and accuracy requirements of a plane control net,and state measuring and position fixing jobs of some special parts of this project.
出处
《施工技术》
CAS
北大核心
2005年第4期75-77,共3页
Construction Technology
关键词
体育场
施工测量
平面控制网
高程
stadium
construction measure
plane control net