一种项目多资源平衡启发式算法 被引量:3

A Heuristic Algorithm For Project Multi-resource Leveling
下载PDF
导出
摘要 针对当前项目所需资源的利用率低而导致项目成本较高的问题,通过对项目的资源优化进行深入研究,给出了资源均衡的目标.在工期一定的情况下,提出了一种项目多资源平衡启发式算法,算法基于对非关键工作,可在其自由时差范围内采取不同的分配方式,可提高资源利用率,从而降低项目成本.经验证,本算法具有有效性且能得到更优解. In project management multiple resource leveling is a problem deserving study. After discussing the basic principle of multiple resource leveling with fixed project duration this paper proposes a heuristic algorithm to solve the problem and gain a satisfactory result. The algorithm is based on the total float of the activity. The activity that has total float can shift some time from the early start time by the algorithm. By adjusting the activity and rescheduling the schedule we can improve the resource utilization ratio and reduce the project cost. At last the algorithm is proved by an instance and the result indicates that we can have a better solution for project multiple leveling by the algorithm.
出处 《哈尔滨理工大学学报》 CAS 2005年第2期37-40,共4页 Journal of Harbin University of Science and Technology
关键词 项目管理 多资源平衡 启发式算法 project management multiple resource leveling heuristic algorithm
  • 相关文献

参考文献4

  • 1朱弘毅.网络计划技术[M].上海:复旦大学出版社,1998..
  • 2BURGES A R, KILLEBREW J B. Variation in Activity Level on a Cyclic Arrow Diagram [ J]. Journal of Industrial Engineering, 1962,13:76 -83.
  • 3白思俊.多资源约束的网络计划的启发式优化方法[J].系统工程理论与实践,1995,15(7):42-47.
  • 4王会玲,刘民,吴澄.启发式算法在网络计划多资源平衡中的应用[J].计算机工程与应用,2003,39(14):226-228. 被引量:7

共引文献14

同被引文献12

引证文献3

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部