摘要
合龙段施工是预应力混凝土连续梁桥施工的重要环节,关系到全桥的受力和线形状况。以某黄河大桥主桥合龙段的施工为工程背景,探讨了预应力混凝土连续梁桥合龙施工的时间选择、合龙方案的选择、合龙顺序、体系转换以及施工配重等方面的内容,为类似桥梁施工提供了有价值的技术资料。
The construction of closure segment is an important step in the construction of prestressed concrete continuous girder bridge and could have direct influences on the stressing conditions and geometry of the overall bridge. With reference to the closure segment construction of the main bridge of a bridge over Huanghe River, this paper studies the selection of time and methods for closure construction, closure sequences, system transformation and construction ballasting for the prestressed concrete continuous girder bridge, and the results of studying provide valuable technical reference to the construction of the similar bridges.
出处
《桥梁建设》
EI
CSCD
北大核心
2005年第2期63-66,共4页
Bridge Construction
关键词
连续梁桥
预应力混凝土结构
悬臂灌筑架桥
合龙
施工方法
continuous girder bridge
prestressed concrete structure
balanced cantilever erection
closure
construction method