摘要
以叶芦沟大桥施工为例,介绍了混凝土箱系梁总体设计方案,阐述了临时结构的设计与实施及现浇箱系梁施工要点,提出了具体的施工控制措施。
Taking the work of Yelugou Bridge as example the integrated design plan of concrete box beam is introduced. According to the temporary structure its design and construction key points of cast-in-site collar beam are elaborated; at the same time practical measures are proposed for construction quality.
出处
《山西建筑》
2005年第12期95-96,共2页
Shanxi Architecture
关键词
预应力大跨度箱梁
现浇方案
控制措施
large-span prestressed box beam, cast-in-site construction, control measure