通渝隧道涌突泥成因分析 被引量:20

Analysis of forming reason of mud breakout in Tong-Yu tunnel
下载PDF
导出
摘要 通渝隧道区分布的含水层属海相沉积而成的可溶岩。2004年2月22日,在隧道中间地段k21+780里程,埋深达940m的隧道左拱肩发生突发性特大涌突泥的地质灾害。运用3D-σ数值分析软件对隧道k21+780地段的围岩进行应力计算,得出了围岩的应力及破坏域分布特征,结合工程地质及隧道施工分析了深埋隧道涌突泥的形成原因。 The water stratum, distributing around the Tong-Yu Tunnel location, is eroded carbonate rock belong sea faces aggradations. A mud breakout was occurring at K21 + 780, with 940-meter depth of rock cover, in Feb 22th, 2004, in Tong-Yu Tunnel. According to the 3D-σ software analysis, the stress in the surrounding rock at K21 + 780 are proved, as well as the breakage region. Based on the conclusion of 3D-σ software analysis, combining with the engineering geology and construction technique, the forming reason of mud breakout in tunnel is discovered.
出处 《岩土力学》 EI CAS CSCD 北大核心 2005年第6期920-923,共4页 Rock and Soil Mechanics
基金 国家自然科学基金重点资助项目(No.50334060)
关键词 隧道 涌突泥 数值模拟 Computer simulation Engineering geology Highway engineering Rock mechanics Stress analysis
  • 相关文献

参考文献6

  • 1.通渝隧道工程地质勘察报告[R].达州: 成都兴蜀基础工程公司达州一三七分公司,2002..
  • 2.复杂条件下长大公路隧道信息施工监测技术研究[R].重庆: 重庆大学, 重庆兴渝公路有限责任公司,2004..
  • 3.省道202线城黔路燕子河至大进段通渝隧道工程涌水段处理设计[R].重庆: 重庆交通科研设计院,2003..
  • 4Mogi K. Fracture and flow of rocks [J]. Tectono-physics, 1972, 13: 541-568.
  • 5Yoshinaka R, Yamabe T. A strength criterion of rockmasses[A]. Proceedings of International Symposium on weak Rock[C]. Tokyo: [s.n.], 1981. 613-618.
  • 6尤明庆.岩石的强度准则及中间主应力的影响[J].河南理工大学学报(自然科学版),2001,23(6):474-478. 被引量:7

二级参考文献8

共引文献6

同被引文献223

引证文献20

二级引证文献259

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部