介绍了李沟高架桥超长钻孔灌注桩采用自平衡法对两根试桩进行静载测试的情况,获得工程设计所需的参数。
This paper illustrates the static load tests of two trial bored piles by means of self-balanced load test method for the very long and large diameter bored piles of Ligou Viaduct on the south section of Suizhou-Yueyang Expressway in Hubei Province, and the process of obtaining parameters necessary for the design of the piles of the Viaduct from the tests.