摘要
碾压沥青混凝土施工在很大程度上受制于天气,恶劣气候地区全年适应沥青混凝土施工的天数非常有限,如何增加其有效施工期非常重要;在四川省南桠河冶勒水电站大坝工程,进行了沥青混合料摊铺层厚30cm、环境气温-6℃以上、日铺筑2层的研究和应用。这些非常规施工方法经过冶勒大坝沥青混凝土防渗心墙施工的实践,证实和验证了其施工质量的可靠性。本文对碾压沥青混凝土的非常规施工进行了介绍。
<Abstrcat>For construction of Yele Hydroelectric Project dam asphalt concrete wall,the asphalt concrete mix was laid in layers of 30cm thick under the ambient temperature above-6℃ and two layers were placed everyday.The hydroelectric project is located on the Nanya River in Sichuan Province.The unconventional practice for construction the dam asphalt concrete cut-off wall demonstrates satisfactory quality & reliability of the construction method.This paper recounts the unconventional construction procedure of the roller compacted asphalt concrete.
出处
《水电站设计》
2005年第2期1-4,共4页
Design of Hydroelectric Power Station
关键词
沥青砼心墙
碾压式沥青砼
碾压试验
层厚
温度
施工方法
冶勒水电站堆石坝
asphlt concrete core
roller compacted asphalt concrete
rolling test
layer thick
temperature
construction method
Yele Hydroelectric Power Station Rockfill Dam