龙滩水电工程施工的索赔和反索赔 被引量:1

Claim and counter claim on the construction of Longtan Hydropower Project
下载PDF
导出
摘要 在龙滩水电工程实施过程中,合同管理是整个项目管理的核心。在业主、监理方面,建立健全了既按国际惯例又符合中国国情的行之有效的合同管理机构,人员配备充实,层次分明。恪守合同是签订施工合同双方当事人的共同义务,索赔是双方当事人各自享有的权利。认真做好索赔和反索赔管理工作,依法保护自身利益,有效地控制工程造价,圆满完成工程建设任务,是业主和承包商双方的共同目标。 Contract management is a core of the whole project management in Longtan Hydropower Project. The Owner and the Supervisor have set up an effective organization with sufficient personnel and clear management duties that conform both to the international practices and Chinese concrete conditions. Strictly following up with construction contract is a common duty for both sides of contract, and claim is the right enjoyed by both sides. Earnestly completing the management work of claim and counter claim, protecting legally one's own benefits in a bid to make each project perfect and satisfied is the target for both sides.
出处 《水力发电》 北大核心 2005年第4期44-46,共3页 Water Power
关键词 水电站施工 合同管理 索赔 管理经验 龙滩水电站 construction of hydropower station contract management claim management experience Longtan Hydropower Station
  • 相关文献

同被引文献3

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部