根据贵阳~新寨高等级公路第三合同段红粘土特性与试验结果,进行填筑试验段施工,分析试验过程和结果,确定合理的施工参数指导红粘土用于路基90区填筑施工。
According to the characteristics and test results of the red clay in Guiyang-Xinzhai Expressway, the construction of backfill test section is carried out. Through analyzing the process and results of tests,the optimum constructive parameters are determined that instruct the red clay to be used for embankment construction in the 90th area of the road bed.
出处
《公路》
北大核心
2005年第6期83-86,共4页
Highway