摘要
某50MW机组自投产以来,运行中一直存在凝汽器真空偏低、17号级缸温超标、5号低压加热器加热效果极差等缺陷,针对上述问题提出了具体的解决办法。
The 50MW steam turbine in Guangzhou Power Plant Co.Ltd. Has been sufferine from such problems as low condenser vacuum,too high temperature of the casing at stage 17 ang low effec of # 5 LP heater since it put into operation. This paper puts forward some solutions to above mentioned problems.
出处
《汽轮机技术》
北大核心
2005年第3期222-224,共3页
Turbine Technology
关键词
凝汽器真空
轴封漏气
轴封段
condenser vacuum
gland leakage
gland segment