偏压连拱隧道施工方法数值模拟研究 被引量:30

Numerical Analysis of Construction Method for Partial Press Double-Arch Tunnel
下载PDF
导出
摘要 结合云南元磨高速公路上的忠爱桥偏压连拱隧道的设计、施工和地质情况,对软弱围岩条件下的公路偏压连拱隧道采用左右两洞不同施工顺序时的力学响应进行了数值模拟,分析了围岩和支护结构在不同施工顺序下的地应力场、位移场,通过对比分析研究,确定了先施作深埋洞,再施作浅埋洞为公路偏压连拱隧道最优施工方案,并且二次衬砌在此条件下不仅是“安全储备”,它对隧道的稳定性有重要作用。 According to design and geological condition of Zhong Ai Qiao tunnel, which lies on the YuanJiang-MoHei Highway, using numerical method the mechanical responses of partial press double-arch tunnel under soft surrounding rock condition in different construction order are analyzed, and then the nonlinear mechanical action's stress field and displacement field are studied, ascertaining that to construct the higher underground hole first then the lower underground hole is the rational construction order of highway partial press double-arch tunnel. And the secondary lining under this condition is not only safety reserve, but also very important factor to the stability of the double arch tunnel.
出处 《地下空间与工程学报》 CSCD 2005年第3期374-378,共5页 Chinese Journal of Underground Space and Engineering
关键词 连拱隧道 偏压 围岩 施工方法 数值分析 主应力 Double-arch tunnel partial press wall rock construction method numerical value analysis main stress
  • 相关文献

参考文献2

  • 1孙钧 侯学渊.地下工程[M].北京:科学出版社,1984..
  • 2蒋树屏.大梅沙隧道施工力学响应及施工方法的研究[R]:科学技术报告[R].,2001,6..

共引文献4

同被引文献194

引证文献30

二级引证文献226

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部