模糊计划评审技术及其在软件工程中的应用

M-PERT and the application of the software engineering
下载PDF
导出
摘要 对软件工程提出一个新的计划评审方法.这一方法以模糊数学理论为基础,项目的每一工序时间用模糊数来描述,项目的总完成时间按模糊数的运算来计算,它克服了经典PERT方法中每一工序时间服从β分布,项目的总时间服从正态分布的假设的局限性.最后将此方法成功地应用于某停车场管理系统的开发中. A new PERT in software engineering is presented in this paper.It is based on fuzzy mathematical theory; every procedure time of project was described by the fuzzy data,and summated by fuzzy computer.It overcomes the localizations of sutra PERT: β-distributing obey to every procedure time and suppose normal distribution to sum time.This method is given following by a successful application to a certain Parking System.
出处 《广西大学学报(自然科学版)》 CAS CSCD 2005年第2期156-159,共4页 Journal of Guangxi University(Natural Science Edition)
关键词 计划评审技术 关键路径 软件工程 模糊数学 项目管理 PERT critical path software engineering fuzzy mathematics project management
  • 相关文献

参考文献5

  • 1McCrimmon K R,Ryavec C A.An analytical study of the PERT assumptions [J].Operations Research,1964,12(1):16-37.
  • 2Moder J J,Phillips C R,Davis E W.Project Management with CPM,PERT and Precedence Diagramming.3rd Ed [M].New York: Van Nostrand Reinhold Company,1983.
  • 3Douglas G Bonett,Richard F Deckro.A multinomial project evaluation and review technique for information systems analysis and design [J].Information & Management,1993,25:51-55.
  • 4Etienne E Kerre(比),黄崇福.模糊集理论与近似推理 [M].武汉: 武汉大学出版社,2004.
  • 5谢洁锐,刘才兴,林丕源,林毅申.基于UML及RUP的通用建模过程及案例分析[J].计算机应用,2004,24(S1):337-338. 被引量:3

二级参考文献2

  • 1(美)PhilippeKruchten著,周伯生等.Rational统一过程引论[M]机械工业出版社,2002.
  • 2[美]SinanSiAlbir著,常晓波.UML技术手册[M]中国电力出版社,2002.

共引文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部