摘要
介绍了杭州湾跨海大桥IX-B标段超长钻孔灌注桩钢筋笼的安装连接方法,并详细说明了套筒挤压连接所用的设备,施工操作前的准备,具体操作要求和操作方法,及施工操作的注意事项。
The method of installation and connection of the reinforcement skeleton for bored piles of Contract Section IX - B of Hangzhou Bay Cross - sea Bridge are introduced. Particularly the faucet squeeze joint technology is described in detail including the equipment needed, preparations before squeezing, squeezing requirement and method, and points of attention, etc.
出处
《石家庄铁道学院学报》
2005年第B06期66-67,共2页
Journal of Shijiazhuang Railway Institute
关键词
钻孔灌注桩
钢筋笼
钢套筒
冷挤压
bored pile
reinforcement skeleton
steel faucet
cold squeeze