摘要
针对高拱坝的工程特点,开发了混凝土高拱坝大坝浇筑施工仿真及可视化系统.此系统不仅考虑缆机之间运行的空间冲突问题,同时考虑缆机生产率的利用问题,并根据大坝不同时期的施工特征,提出了分阶段模拟的思想来调整实际进度计划.最后应用此系统对某大坝浇筑施工方案进行了论证,为混凝土浇筑施工方案的优化提供依据.
According to the characteristics of high concrete arch dam construction, the simulation and (visualization) system of the high concrete arch dam is developed. The system not only concerns the spatial (conflict) problems between cable-cranes, but also involves the effective use of cable-cranes'productivity (simultaneously.) Considering the different construction features during different phases, the idea of simulating by phases is (presented) to adjust practical construction schedule. Through applying the system into the example of Xiaowan (Hydropower) Project, the construction scheme is verified and finally the optimal scheme is proposed.
出处
《天津大学学报(自然科学与工程技术版)》
EI
CAS
CSCD
北大核心
2005年第7期625-629,共5页
Journal of Tianjin University:Science and Technology
关键词
拱坝
混凝土浇筑
缆机
仿真
arch dam
concrete construction
cable-crane
simulation