为在具体施工中推广折线先张法技术,介绍了折线先张梁长线法中抗拔桩的设计、张拉台座的设计、转向装置的设计、转向装置摩阻力的试验等研究工作。
To introduce the fold line pre-tension technology in practical projects, authors state some study works of the long line method of fold line pre-tension beams such as design of uplift piles, tension bases and transfers and tests of frictional resistance of transfers and so forth.=
出处
《施工技术》
CAS
北大核心
2005年第7期31-32,69,共3页
Construction Technology
基金
河北省交通厅资助项目(Y01101)
关键词
预应力混凝土梁
先张法
长线法
摩阻试验
prestressed concrete beam
pre-tension method
long line method