摘要
磨溪气田80×104m3/d装置经过9.5个月的试运行,现已正式通过验收,本文对该工艺装置(脱硫、脱水、回收)的试运状况进行了总结,同时对装置特点及存在问题进行了评析。尤其是1.2.3级组合冷凝冷却器在三个月内腐蚀报废值得我们思考。
After 9.5 months trial run,the 800 × 103m3/d gas treating equipment has passed the check.The paper sums up the trial run situation (desulfurization, dehydration and sulfur recovery),while author analysizes the device characteristics and existing problems.Especially it is worth considering that the combined condenser-cooler was corrupted and rejected within 3 months.
出处
《石油与天然气化工》
CAS
CSCD
北大核心
1995年第3期153-155,共3页
Chemical engineering of oil & gas