本文介绍了邯郸中板厂二期改造托梁截柱工程的施工和监测技术,在不停产条件下,为了实施加大柱距,施工中采用了安装平台和应力平台,同时实行了监测手段,给出了详细的施工过程和监测结果,为同类工程提供了可靠依据和办法。
The construction and monitoring technique of cutting columns supported with bracket is introduced herein for project of Handan coddle plate plant.Under the condition of production,installation and stress platforms were used for enlarging the columns' space.Meanwhile,the monitoring system was applied.Detailed construction process and monitoring results are presentet in this paper which provides reliable basis and method for similar projects.