摘要
本文仅对大沙河水库渗漏量较大的灯山副坝采用高压定向喷浆处理坝下河床和坝体劈裂灌浆解决渗漏问题及其效果进行分析和论述。
Abstract:The paper analyses and describes the high pressure directional jet grouting for the treatment of the river bed below the dam foundation and the fracturing grouting in the dam for solving the seepage problem as well as their effects. The two kinds of grouting are used in Dengshan auxiliary dam with large seepage quantity and the highest dam in Deshahe Reservoir.