半导体硅片加工过程复合控制策略研究及仿真 被引量:5

Research and Simulation of Compound Controlling Strategy in Semiconductor Wafer Fabrication
下载PDF
导出
摘要 复合优先级控制策略CPC是一种兼顾投料与调度策略的生产过程综合控制策略。通过比较加工任务的复合优先级系数,CPC策略能够确定下一个加工任务,以及决定何时投放新工件。CPC策略甚至能够暂停非瓶颈设备以避免瓶颈设备前的在制品堆积。仿真结果表明,这种复合控制策略是一种能够同时优化多种性能指标的生产过程控制策略,可降低加工周期及其方差,减少生产过程中的在制品数,提高设备利用率及生产率等。 A new compound priority control strategy, CPC, is discussed, which integrates the scheduling and lot release policies into a whole. The compound priority measure is composed by seven sub-priority items. By comparing the compound priorities of jobs that compete with for processing, the CPC strategy can determine which lot(s) is/are processed when the machine is available, and when the new lot(s) is/are released into the wafer fab. The CPC can halt the non-bottleneck machines to prevent overstock of WlP before the bottleneck machines. The simulation results indicate that the CPC strategy has higher performance in reducing the cycle time and its standard deviation, decreasing the WIP inventory, and increasing utilization of machines and fab's throughput rate.
出处 《系统仿真学报》 EI CAS CSCD 北大核心 2005年第8期1924-1927,1950,共5页 Journal of System Simulation
基金 973项目子课题(2002CB312202-03) 国家自然科学基金(60374005)
关键词 半导体 硅片加工 控制策略 调度策略 投料策略 仿真 semiconductor wafer fabrication control scheduling lot release simulation
  • 相关文献

参考文献14

  • 1王然,吴澄.智能规则在半导体生产线调度中的应用[J].计算机集成制造系统-CIMS,1997,3(4):33-35. 被引量:7
  • 2Oey K, Mason S J. Scheduling Batch Processing Machines in Complex Job Shops [J]. Proceedings of the 2001 Winter Simulation Conference, 1200-1207.
  • 3Kumar P R. Re-entrant Lines [J]. Queuing Systems, 1993, 13(2): 87-110.
  • 4Wein L M. Scheduling Semiconductor Wafer Fabrication [J]. IEEE Transactions on Semiconductor Manufacturing, 1988, 1(3): 115-130.
  • 5Kumar P R. Scheduling Semiconductor Manufacturing Plants [J]. IEEE Transactions on Semiconductor Manufacturing, 1994, 9(1): 33-40.
  • 6Spearman M L, Woodruff D L, Hopp W J. CONWIP: A Pull Alternative to Kanban [J]. International Journal of Production Research, 1990, 28(5): 879-894.
  • 7王中杰.[D].上海同济大学,2000.
  • 8Lu S H, Kumar P R. Distributed Scheduling Based on Due Dates and Buffer Priorities [J]. IEEE Transactions on Automatic Control, 1991, 36(12): 1406-1416.
  • 9Dabbas R M, Chen H N, Fowler J W, Shunk D. A Combined Dispatching Criteria Approach to Scheduling Semiconductor Manufacturing Systems [J]. Computers& Industrial Engineering, 2001, 39: 307-324.
  • 10Morrison J, Janakiram M, Kumar P R. A. Comparative Study of Scheduling Policies at Motorola Fabs [A]. Proceedings of the International Conference on Semiconductor Manufacturing Operational Modeling and Simulation [C]. 1999, San Francisco, CA: 51-56.

共引文献6

同被引文献33

引证文献5

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部