工程系统可靠度的逻辑分析与优化设计 被引量:1

Logical analysis and optimun design of engineering system reliability
下载PDF
导出
摘要 基于结构逻辑图的理论,提出了以下确界算子和上确界算子分别作为串联与并联系统可靠度的计算模型;形成了复杂工程系统可靠度的逻辑分析方法。在此基础上,应用多阶段决策算子法,成功地求解了工程系统可靠度的优化设计问题;给出了桁架结构优化的数值计算例题。 In this paper,based on the theory of structure logic paradigm,computational model ofsystem reliability is presented by using infimum operator and supremum operator corre-sponding concatenate and parallel systems respectively,which formed logical analysismethod for complex engineering system reliability. Employed this computational model,theoptimum design of engineering system reliability is solved successfully by using the multi-stage decision operator method.A numerical example computed of structure optimization oftruss is given in this paper.
作者 王文涛
出处 《计算结构力学及其应用》 CSCD 1995年第4期429-437,共9页
关键词 系统可靠度 优化设计 结构逻辑图 桁架 优化 system reliability optimal designs/structure logic paradigm multistage decision operator method optimum reliability of truss
  • 相关文献

同被引文献27

  • 1白宝光,张世英.质量成本模型及其优化[J].科学管理研究,2005,23(3):29-31. 被引量:29
  • 2钱刚,郑胜国,汪小年.串联系统可靠性设计的一种实用算法[J].移动电源与车辆,2005,36(2):14-17. 被引量:3
  • 3杨耀红,汪应洛,王能民.工程项目工期成本质量模糊均衡优化研究[J].系统工程理论与实践,2006,26(7):112-117. 被引量:55
  • 4刘晓峰,陈通,张连营.基于微粒群算法的工程项目质量、费用和工期综合优化[J].土木工程学报,2006,39(10):122-126. 被引量:40
  • 5Siemens N. A simple CPM time-cost trade-off algorithm [J].Management Science, 1971,17 (6) : 354-363.
  • 6Philips S, et al. Solving the project time-cost trade- off problem using the minimal cut concept [J ]. Management Science, 1977,24 (4) : 393-400.
  • 7PremVrat, et al. Goal program-ming model for project crashing with piece wise linear time-cost trade-off [J]. Engineering Costs and Production Economics, 1986,10(2) : 161- 172.
  • 8Deckro R F, et al. Nonlinear time-cost trade-off models in project management [J].Computers & Industrial Engineering, 1 995,28 (2) : 219 - 229.
  • 9Do Ba Khang, et al. Time, cost and quality trade-off in project management: A ease study [J]. Inter- national Journal of Project Management, 1999 : 249- 256.
  • 10Azaron A,Tavakkoli-Moghaddam R. Multi-objective time-cost trade-off in dynamic PERT networks using an interactive approach[J]. European Journal of Operational Research, 2007,180 (3) : 1186 - 1200.

引证文献1