摘要
为谋求进一步发展,某铝业公司决定建设热轧生产线,因此需要对原110 kV 变电所进行扩容改造。本文提出了两种改造方案,并详细地分析了各自的优缺点。其中一个方案已被该公司采用。
To strive for further development, an aluminum processing company has decided to add an aluminum hot rolling line, so needs to revamp and expand the original 110kV substation. The paper puts forward two design schemes for revamping the substation,and analyzes in detail the advantages and shortages of each scheme. One of the schemes has been adopted by the company.
出处
《有色金属加工》
CAS
2005年第4期54-55,共2页
Nonferrous Metals Processing