摘要 结合土建工程施工安全风险管理的特点,提出了WBS-RBS与AHP相结合的土建工程施工安全风险评估方法,把评估过程分为工程项目资料调研、风险辨识、风险衡量和风险度计算4个步骤,并详细介绍了WBS-RBS风险辨识方法、专家调查风险衡量方法和AHP风险度计算方法在土建工程施工安全风险评估中的应用。WBS-RBS与AHP相结合的土建工程施工安全风险评估方法在系统分析计算的基础上,能够全面的辨识土建工程项目施工安全的典型风险和计算总的风险度,为工程项目的施工安全风险评价提供了一个可行的方法和为有效防范风险奠定了基础。 Based on the characteristics of civil engineering construction construction safety, a combined method of WBS-RBS and AHP for evaluating the risk of civil engineening construction safety is presented, The evaluation process composes of four steps, i.e. ergineering project data investigation, risk recognition, risk evaluation and risk calculation. The WBS-RBS method used in the risk recognition, risk evaluation used by expert investigation, and risk calculation of the AHP method employed are introduced in detail. The combined method of WBS-RBS and AHP could be used to fully recognize typical risks of construction safety in civil engineering project and to calculate the total risk pttwiding a feasible method for the risk evaluation of civil engineering construction and laying the foundation of effective risk prevention.
出处 《中国安全科学学报》 CAS CSCD 2005年第7期101-103,107,共4页 China Safety Science Journal
关键词 土建工程 施工管理 安全管理 风险管理 WBS-RBS AHP法 Engineering insurance Risk of project construction safety Risk WBS-RBS (Work Breakdown Structure-Risk Breakdown Structure) AHP(Analytic Hierarchy Process)
  • 相关文献

参考文献5

二级参考文献22

  • 1Johnson P.Evolution of risk concept.
  • 2Smelley P. The Importance of comprehensive risks management programs for large projects.
  • 3Clark G T.Addressing risk in seattle's underground.
  • 4Ott K R.A Risk assessment and analysis for an existing water conveyance tunnel.
  • 5Rozek J.Singapore's deep tunnel sewerage system:risk management form conceptual design to construction.
  • 6Brenner B.Design for construction mitigation on boston's central artery/tunnel projects.
  • 7Stepherd A.Systems engineering applications in railways.
  • 8屈晓辉.秦沈客运专线主要设计技术[M].,..
  • 9BellDE schlerferAJr.风险管理[M].哈佛大学,..
  • 10朱庆杰 苏幼坡 刘廷权.灾害危险性评价的神经网络预测模型[J].电子与信息学报,2003,25:17-22.

共引文献87

同被引文献296

引证文献61

二级引证文献271

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部