摘要
采用双排灌注桩加环压梁形成基坑围护,辅以分段开挖、外围卸土的措施,使深基坑施工有了安全保证。
Safety construction of deep foundation pit is guaranteed by forming pit enclosure with double-row poured-in-place pile plus ring beam, and by the adoption of some measures, such as digging section by section,outside soil discharge and so on.
出处
《建筑施工》
1995年第1期4-6,共3页
Building Construction
关键词
深基坑
围护结构
设计
工程施工
foundation pit
enclosure structure
construction