国产引进型300 MW机组大修周期延长的要素分析及应对策略 被引量:1

Essentials of overhaul interval extension for 300 MW domestically-made imported type units and the corresponding strategy
原文传递
导出
摘要 根据对上海汽轮机厂生产的300MW引进型机组的调研情况,结合外高桥发电厂1号机组实际运行和检修情况,从安全性和经济性两方面分析了制约大修周期延长的基本因素。通过分析比较和有针对性地对检修级别和检修内容的调整,以及优化检修工作的逐步开展和机组性能优化管理系统(OPM)的充分应用,使1号机组的大修周期从4年延长到6年在安全性和经济性方面得到保证,并提出需进一步加强的工作。 According to the investigation and research on the 300 MW imported type unit manufactured by Shanghai Turbine Co. , Ltd. , and combining the operation and maintenance condition of the No. 1 unit of Shanghai Waigaoqiao Power Generation Co. , Ltd. , the primary factors restricting the overhaul interval extension of the units are analyzed in the aspects of safety and economy. Through analytic comparison and adjustment of maintenance level and contents,and after the implementation of optimization maintenance and the full application of Optimal Performance Management System ( OPM), the overhaul interval of the No. 1 unit was extended from 4 years to 6 years, while the safety and economy of the unit were ensured. The work needing further efforts is also put forward.
出处 《华东电力》 北大核心 2005年第7期49-53,共5页 East China Electric Power
关键词 汽轮机 大修周期 安全性 经济性 steam turbine overhaul interval safety economy
  • 相关文献

参考文献3

二级参考文献6

  • 1.N300-16.7/537/537 300 MW中间再热凝汽式汽轮机热力性能数据[R].上海汽轮机厂,1994..
  • 2汤卫平.发电厂GH4145/SQ镍基高温合金螺栓运行安全性研究[R].华东电力试验研究院,..
  • 3.马鞍山第二发电厂300MW机组汽缸螺栓断裂原因研究[R].电力部热工研究院,1999..
  • 4华北电力科学研究院.电力工业技术监督标准汇编(金属分册)[R].,1994..
  • 5.高、中压内缸螺栓有限元应力计算与分析嘉兴发电厂300MW机组高中压内缸螺栓断裂原因研究(课题总结报告之五)[R].浙江大学力学系,2001..
  • 6赵英和.秦皇岛热电厂高温镍基合金螺栓断裂原因分析[J].中国电力,1999,32(7):18-21. 被引量:5

共引文献10

同被引文献43

引证文献1

二级引证文献24

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部