对于混凝土面板堆石坝填筑的边角处理一直是个难题,主要总结了吉林台一级水电站大坝填筑在边角处理上的一种新的施工工艺,就是对边角进行斜坡碾压。
The treatment of the unfilled edge and corner on the embankment of the concrete face rock fill dam is a difficult problem during the construction of the dam. A new construction technology to solve the problem is described herein, that is to treat the unfilled edge and corner on the embankment with the inclined rolling.
出处
《水利水电技术》
CSCD
北大核心
2005年第8期33-34,共2页
Water Resources and Hydropower Engineering