张钢2号高炉于1992年4月采用了综合布料技术,合理进行上部调剂,取得了炉况顺行、高炉煤气流分布合理、节焦增产的冶炼效果。
In april 1992 the comprehensive burden distribution and suitable upper conditioning were conducted in No2 BF at Zhangdian I & S works.The operational results were obtained as follows;a smooth operation of BF,reasonable gas flow distrbution coke saving and production increasing.
出处
《炼铁》
北大核心
1995年第1期24-26,共3页
Ironmaking
关键词
高炉
布料
装料制度
装料
blast furnace,burden distribution,charging schedule