摘要
本文对韩城电厂东侧横山滑坡体测斜孔监测资料进行了分析与计算,指出该滑坡体为浅层滑和深层滑动组成的多滑动面的滑坡体。得出了经过工程治理,取得了缓解滑动的效果,但没有完全根治,近期滑坡体又有加速蠕动之趋势的结论。
Based on analysing and calculating of the monitoring data of the Hengshan landslide bodyat the eastern side of Hancheng Power Plant,it is presented that the Hengshan landslide body has several shallow slide planes and deep slide planes and it is concluded that recently the landslide body hastrend to creep rapidly though it has been treated by engineering means.
出处
《陕西水力发电》
1995年第2期6-10,共5页
Journal of Shaanxi Water Power
关键词
发电厂
滑坡
斜孔
监测
观测资料