长引水隧洞水电站差动式调压井最不利工况研究 被引量:5

Study on the differential surge tank in a power plant with a long approach tunnel under the most unfavourable operation condition
下载PDF
导出
摘要 以我国西南某大型水电站引水调压井中用作升管的闸门井坍塌事故作为例子,通过计算分析,说明在这一类调压井的设计中,不能沿用单一的甩(或增)荷工况作为控制工况,应考虑连续增甩负荷可能会造成调压井内涌浪的不利叠加,此外还应考虑在各种不利工况叠加下升管与大井之间的水位差. In this paper, calculations are carried out to simulate the collapse processof gate well which is used as a riser pipe of the differential surge tank of a largepower plant in China. It is shown by calculation that after a series of loading andunloading, a large water level difference between the tank and riser pipe happened,thus accident occured. Further analysis indicates that the single unloading operation is not the most unfavorable operation condition. The probablesuperimposition of surges due to continuous loading and unloading and the corresponding water level difference between the surge tank and riser pipe should betaken into account during design.
出处 《水利学报》 EI CSCD 北大核心 1995年第6期22-30,共9页 Journal of Hydraulic Engineering
关键词 差动式调压井 升管 水位差 甩荷 引水隧洞 e differential surge tank, loading, unloading, riser pipe, waterlevel difference.
  • 相关文献

参考文献2

共引文献6

同被引文献33

引证文献5

二级引证文献18

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部