摘要
陈村大坝坝基地质条件复杂,本文简述F11、F31、F32、F35四条大断层的危害及处理过程,依据测缝计、倒垂线、扬压力和渗漏量等监测设施所获取的大量信息,对各项处理措施的效果,进行反馈研究。
The geological condition of Chencun Dam foundation is complicated. This Paper introduces the jeopardy four large faults F,,,F,,,F,2 and F,,bring about to the Dam and theprocess of treatment. The feedback study is performed for each treatment effect,on thebasis of observation data from jointmeters, plumb lines, and other monitoring instruments.
出处
《水力发电学报》
CSCD
北大核心
1995年第1期49-58,共10页
Journal of Hydroelectric Engineering
关键词
重力拱坝
坝基
断层
渗漏
监测
处理
Chencun Dam foundation Fault treatment Monitoring